How to calculate concrete:
- Determine how thick you want the concrete.
- Measure the length and width that you’d like to cover.
- Multiply the length by the width to determine square footage.
- Convert the thickness from inches to feet.
- Multiply the thickness in feet by the square footage to determine cubic feet.
How much does a 30×30 concrete slab cost?
How much does a cubic foot of concrete cost?

How much is concrete per square yard?
Concrete Estimating
Students will learn to accurately estimate concrete costs. Using a real set of drawings, students will perform a complete concrete takeoff and will apply material and labor costs to that takeoff to assemble a complete estimate. Students will leave this class with the knowledge needed to produce accurate concrete estimates using efficient and reliable estimating techniques.
|
|
Traditional Concrete Visualization & Estimation Methods:
- Estimating slab in cubic feet: multiply the length by the width by the depth of the desired slab in inches, then divide by 1728 to calculate the slab’s total cubic feet (don’t forget to add ten percent to adjust for variations and waste)
- For cubic yards: follow the steps above and divide by 27
- Visualizing a cubic yard: Imagine a 9’ x 9’ slab at 4” deep, or approximately five sidewalk squares
- 1 cubic yard of concrete placed at 4-inches deep will cover 81 square feet
- one pallet of 56, 60-pound bags of Sakrete mix is roughly one cubic yard of concrete (considering waste: add about 4 additional bags are of 60-pound mix for full cubic yard)
How much concrete do I need for a 10×10 slab
To determine the how much concrete do I need for a 10×10 slab solve in following steps:-
Step 1 :- calculate the volume in cubic feet:- we have given 10×10 slab (length × width), consider it is 4 inch thick, 4 inch = 0.33 feet, to determine the volume of slab, you need to multiply all dimensions, such that = 10′ × 10′ × 0.33′ = 33 cubic foot.
Step 2 :- converting cubic feet into cubic yard:- now converting into cubic yard, you should divide it by 27, because 1 cubic yard = 27 cubic foot, so volume of concrete you needed for 10 × 10 slab 4 inch thick in cubic yard = 33/27 = 1.23.
Step 3 :- Add 10% extra :- considering extra 10% wastage during mixing and pouring, so 10% of 1.23 cubic yard = 0.123, add 1.23 + 0.122 = 1.35 cubic yard.
How much concrete do I need for a 10×10 slab
Regarding this, “how much concrete do i need for a 10×10 slab?”, generally you will need 1.23 cubic yards of premixed concrete for a 10×10 slab at 4 inches thick, at 5 inches thick you will need 1.54 cubic yards of concrete and at 6 inches thick – 1.85 cubic yards of concrete. Always you should purchase 5 to 10% more premixed than required.
4″ thick slab of 10×10 is ideal in normal load or standard condition for making sidewalks, curbs, steps, ramp, walkway and patio and 5 inch or 6 inch thick slab is ideal for heavy load and heavy traffic
How many yards of concrete do I need for a 10×10 slab
One may ask a reasonable question, “how many yards of concrete do I need for a 10×10 slab?”, generally there are 1.23 cubic yards of premixed concrete you will need for a 10×10 slab at 4 inches thick, at 5 inches thick you will need 1.54 cubic yards of concrete and at 6 inches thick – 1.85 cubic yards of concrete.
How many cubic feet of concrete do I need for a 10×10 slab?
One may ask a reasonable question, “how many cubic feet of concrete do I need for a 10×10 slab?”, generally there are 33.21 cubic feet of premixed concrete you will need for a 10×10 slab at 4 inches thick, at 5 inches thick you will need 41.58 cubic feet of concrete and at 6 inches thick – 49.95 cubic feet of concrete.